Key Facts

  • Client Name:
    London Borough of Waltham Forest
  • Principal Contractor:
    Mace Group PLC
  • Contract Administrator:
    NPS Group
  • Address:
    Walthan Forest Schools
    Barrett Road
    Walthamstow
    E17 3ND
  • Value of Works:
    £2,400,000
  • Start Date:
    July 2011
  • End Date:
    October 2011

Scope of Works

The complete refurbishment of the four schools listed below in which all critical operations had to be completed during the children's summer holiday.

  1. Warwick North (Woodside Primary School) - Block A (Ground & Mezzanine), BlockB & Block C, Barrett Street
  2. Warwick South (St Mary's C of E Primary School), Brooke Road
  3. Edinburgh Primary School
  4. Chapel End Primary School
  • Internal Demolition & Strip out
  • Builders Work and Internal Drainage Connections
  • Metal & Glass Canopies Including Final Design
  • Dry Lining WC Fit Out
  • Staff Kitchenette Fit Out
  • Suspended Ceilings
  • Plastic, Carpet & Refurbishment of Existing Parquet Flooring
  • Door Sets, Ironmongery and Joinery Including Refurbishment of Existing Sash Windows
  • Painting & Decorating

Walthan Forest Schools Gallery